What this article covers: How to use the Consolidation Runs page in BrizoConsol — checking when the group was last consolidated, whether each run finished, and what each run did.

BrizoConsol consolidates the group automatically — you do not run consolidation yourself. The Consolidation Runs page is where you check it: whether a consolidation is running now, when the last one completed, and the history of runs, whatever started them.

1. Accessing the Page

Go to Settings → Global Settings → Consolidation Runs (under System) from the left navigation. The menu item is available to users with Administrator access.

2. The Status Card

The card at the top shows the group’s consolidation status:

Status What it means
A run is in progress. Reports show the previous figures until it finishes; the page keeps itself up to date while it runs.
The scenario and time of the last completed run, and how long ago it finished.
The latest run failed or was stopped, with the error where there is one.
No run has been recorded for the group yet.

Below it, one panel per scenario — Actual, Forecast and Budget — shows the result of that scenario’s latest run and when it last completed. A scenario with no figures shows No figures yet.

3. Run History

The Run history table lists the runs of the last 90 days, newest first:

Column Description
When the run started.
Actual, Forecast or Budget.
The reason for the run, such as Group structure saved (Recalculation otherwise), and who started it — a user, or System.
How long the run took.
Completed, Failed, Running or Stopped.

Use the All scenarios and All results lists above the table to filter it. Click a run to see when it started and finished, each step it went through — Done or Nothing posted — and the error if it failed.

💡 Tip: If figures look out of date, check here first: a run that is still going or did not finish explains why the reports show earlier figures.